Skip to content

Refusals and conditions

From the council's decision notices

Laois: why applications are refused, and the conditions permissions carry

Counted from Laois’s own decision notices: 538 of its 573 decisions made from 24 November 2025 to 24 November 2026 (94%). Findings, not verdicts — each figure is a share of the notices read.

Decision notices read
538
of 573 decisions, last 12 months
Refusals read
36
of 39 refused or part refused
Permissions read
491
of 534 granted or part granted
Conditions on a permission
10
the median permission read

Why applications are refused

Grounds cited in refusals

Share of 36 refusals whose decision notice we read

  1. Contrary to development plan policy81%
  2. Traffic safety, access and sightlines53%
  3. Undesirable precedent33%
  4. Neighbours' amenity (overlooking, overshadowing, overbearing)25%
  5. Density, layout and residential standards19%
  6. Other19%
  7. Flood risk17%
  8. Insufficient information17%
  9. Rural housing policy and local need14%
  10. Zoning and land use14%
  11. Design, scale and visual impact11%
  12. Protected structures, ACAs and archaeology8%

A notice counts once for each theme it cites, however often it cites it — the share of refusals refused at least partly on that ground. A notice can cite several, so the shares do not add up to 100%.

Show the numbers
ThemeNoticesShare
Contrary to development plan policy2981%
Traffic safety, access and sightlines1953%
Undesirable precedent1233%
Neighbours' amenity (overlooking, overshadowing, overbearing)925%
Density, layout and residential standards719%
Other719%
Flood risk617%
Insufficient information617%
Rural housing policy and local need514%
Zoning and land use514%
Design, scale and visual impact411%
Protected structures, ACAs and archaeology38%

The conditions permissions carry

Kinds of condition attached

Share of 491 permissions whose decision notice we read

  1. Built as per the plans and particulars100%
  2. Protecting neighbours (screening, glazing, noise, light)90%
  3. Materials, finishes and design changes88%
  4. Surface water and drainage (SuDS)87%
  5. Entrance, sightlines, roads and parking85%
  6. Restrictions on use or further development82%
  7. Development contributions and security bonds78%
  8. Construction hours and management70%
  9. Waste management69%
  10. Other51%
  11. On-site wastewater treatment system44%
  12. Landscaping, hedgerows, trees and boundaries43%

A notice counts once for each theme it cites, however often it cites it — the share of permissions given at least one condition of that kind. A notice can cite several, so the shares do not add up to 100%. The 12 most common of 20 are drawn; the table has them all.

Show the numbers
ThemeNoticesShare
Built as per the plans and particulars491100%
Protecting neighbours (screening, glazing, noise, light)44390%
Materials, finishes and design changes43088%
Surface water and drainage (SuDS)42787%
Entrance, sightlines, roads and parking41985%
Restrictions on use or further development40582%
Development contributions and security bonds38378%
Construction hours and management34470%
Waste management34169%
Other25151%
On-site wastewater treatment system21844%
Landscaping, hedgerows, trees and boundaries21343%
Uisce Éireann water and sewer connections18237%
Energy, EV charging and climate13527%
Occupancy and local-need conditions10020%
Duration or temporary permission6313%
Ecology (bats, nesting birds, AA mitigation)449%
Archaeology and built heritage316%
Estate completion, lighting, naming and taking in charge245%
Part V social housing163%

By type of development

The grounds cited in refusals and the conditions attached in Laois, by type of development
TypeNotices readRefusals: most citedPermissions: most common conditions
Agricultural4291% of decisions1 read — too few
  1. Construction hours and management95%
  2. Entrance, sightlines, roads and parking95%
  3. Protecting neighbours (screening, glazing, noise, light)95%
Alterations3895% of decisions—
  1. Materials, finishes and design changes76%
  2. Duration or temporary permission58%
  3. Entrance, sightlines, roads and parking58%
Extension7590% of decisions—
  1. Materials, finishes and design changes97%
  2. Surface water and drainage (SuDS)97%
  3. Restrictions on use or further development93%
New dwelling13994% of decisions21 read — too few
  1. Development contributions and security bonds100%
  2. Materials, finishes and design changes98%
  3. Entrance, sightlines, roads and parking95%
Retention11994% of decisions2 read — too few
  1. Protecting neighbours (screening, glazing, noise, light)91%
  2. Surface water and drainage (SuDS)90%
  3. Development contributions and security bonds88%

Shares are of the refusals or permissions whose notice was read. The conditions column leaves out “built as per the plans and particulars”, which nearly every permission carries. A group with fewer than 30 notices read shows its count and no breakdown.

By town

Towns with at least 30 refusals or permissions read, listed alphabetically.

The grounds cited in refusals and the conditions attached in Laois's towns, listed alphabetically
TownNotices readRefusals: most citedPermissions: most common conditions
Portlaoise5094% of decisions5 read — too few
  1. Restrictions on use or further development95%
  2. Surface water and drainage (SuDS)95%
  3. Protecting neighbours (screening, glazing, noise, light)93%

Shares are of the refusals or permissions whose notice was read. The conditions column leaves out “built as per the plans and particulars”, which nearly every permission carries. A group with fewer than 30 notices read shows its count and no breakdown.

About the figures

PPI’s reader reads each decision notice, finds every refusal reason and condition in it word for word, and tags each with what it is about from a fixed list. A figure counts notices: a refusal citing flood risk in two of its reasons counts once for flood risk. Reasons and conditions the reader could not find word for word are not counted.

What a council refuses for, and the conditions it attaches, depend on what it was asked to decide as much as on the council. A group with fewer than 30 notices read shows its count and no breakdown. Every council read →

Source Laois's decision notices, read and counted by PPI; no notice text is reproduced hereAlways confirm a decision against the council’s own register.

Independent planning information for Ireland — not a government website or an official planning service, and not legal advice. Contains Irish Public Sector Data licensed under CC BY 4.0. Always confirm details with the relevant local authority before relying on them.

Planning portal

Free pre-planning reportCheck a site before you apply
Map of applicationsEvery application on one map, with zoning and heritage layers
AreasCounties and towns
Planning statisticsThe national picture, and every council side by side
CommencementsWhat actually got built
Property salesWhat it sold for
Ask the planning assistantPlain-English questions