New Judicial Review Rules and Statutory Timelines Brought into Force Under Planning Act

Tuesday 24 November 2026

Commencement orders signed under the Planning and Development Act 2024 introduce new judicial review rules and statutory decision timelines across the Irish planning system.

Commencement orders bringing new judicial review rules and statutory planning timelines under the Planning and Development Act 2024 into effect have been signed.

Housing Minister James Browne signed orders bringing further sections of the Act into operation, with the measures taking effect from Thursday.

Under the commenced provisions, applicants initiating judicial review proceedings against planning decisions must demonstrate a "sufficient interest". The changes also place restrictions on altering legal pleadings during an ongoing case and eliminate the further appeal stage to the Court of Appeal.

In addition, the preliminary requirement to seek court permission prior to bringing a judicial review has been removed, a change the government states will reduce legal fees and procedural delays.

For developments facing legal challenges, planning permissions subject to judicial review will now be paused, preventing time spent before the courts from eroding the lifespan of the permission.

The commenced measures also introduce mandatory statutory decision-making timelines across the wider planning process, including for An Coimisiún Pleanála. Browne stated that these adjustments address "an overly drawn out process with hoops to jump at every turn, many of them unnecessary", while facilitating minor corrections to applications.

Free pre-planning reportCheck a site before you apply
Map of applicationsEvery application on one map, with zoning and heritage layers
AreasCounties and towns
Planning statisticsThe national picture, and every council side by side
CommencementsWhat actually got built
Property salesWhat it sold for
Ask the planning assistantPlain-English questions